Question # 1 Test Management Assume you are managing the system testing phase of a project. The system test execution period is scheduled to twenty weeks. All tests are manual tests. You are following a risk-driven test approach. During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests. Which of the following would you expect to be the best way to respond to this situation? Number of correct responses: 1 K2 1 credit
A. Prioritize executing the tests for the highest product risks and track these risks
B. Remove testers from your test team, so that they can be assigned to other projects
C. Automate all remaining tests
D. No action is needed, test as much as possible in the remaining time period
Click for Answer
A. Prioritize executing the tests for the highest product risks and track these risks
Question # 2 Test Management For which of the following activities would the costs be classified as a cost of detection? Number of correct responses: 1 K2 1 credit
A. Writing test specifications according to the test design
B. Training developers to better understand the new features of the coding language they will use on the project
C. Re-running a test case, during the system testing phase, to verify that a fix eliminates a previously found defect
D. Fixing field failures
Click for Answer
A. Writing test specifications according to the test design
Question # 3 Reviews You are the Test Manager of a project that adopts a V-model with four formal levels of testing: unit, integration, system and acceptance testing. On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, lowlevel design and code have been performed prior to testing. Assume that no requirements defects have been reported after the release of the product. Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness? Number of correct responses: 2 K3 2 credits
A. Number of defects found during the requirements review
B. Total number of defects attributable to requirements found during unit, integration, system and acceptance testing
C. Total number of defects found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
D. Time to conduct the requirements review
E. Total number of defects attributable to requirements, found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
Click for Answer
A. Number of defects found during the requirements review
E. Total number of defects attributable to requirements, found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
Question # 4 Which of the following statements represents the most effective contribution of the stakeholders to the completion of the failure mode analysis table? Number of correct responses: 1 K4 3 credits
A. The aircraft pilot and the customer representative should contribute to assess the detection. The chief software engineer, the system architect and the expert tester should contribute to assess the priority.
B. The aircraft pilot and the customer representative should contribute to assess the priority. The chief software engineer, the system architect and the expert tester should contribute to assess the detection.
C. The system architect and the chief software engineer should contribute to assess the priority. The expert tester is the only one who should contribute to assess the detection.
D. The aircraft pilot is the only one qualified to contribute to assess the priority and thus should be assigned this task. The customer representative should contribute to assess the detection.
Click for Answer
B. The aircraft pilot and the customer representative should contribute to assess the priority. The chief software engineer, the system architect and the expert tester should contribute to assess the detection.
Question # 5 Testing Process Assume you are the Test Manager for a new software release of an e-commerce application. The server farm consists of six servers providing different capabilities. Each capability is provided through a set of web services. The requirements specification document contains several SLAs (Service Level Agreements) like the following: SLA-001: 99.5 percent of all transactions shall have a response time less than five seconds under a load of up-to 5000 concurrent users The main objective is to assure that all the SLAs specified in the requirements specification document will be met before system release. You decide to apply a risk-based testing strategy and an early risk analysis confirms that performance is high risk. You can count on a well-written requirements specification and on a model of the system behavior under various load levels produced by the system architect. Which of the following test activities would you expect to be the less important ones to achieve the test objectives in this scenario? Number of correct responses: 1 K4 3 credits
A. Perform unit performance testing for each single web service
B. Monitor the SLAs after the system has been released into the production environment
C. Perform system performance testing, consisting of several performance testing sessions, to verify if all the SLAs have been met
D. Perform static performance testing by reviewing the architectural model of the system under various load levels
Click for Answer
B. Monitor the SLAs after the system has been released into the production environment
Question # 6 Test Management Which of the following statements best describes an appropriate approach for managing exploratory testing? Number of correct responses: 1 K2 1 credit
A. Define very detailed mission statements, which allow testing work to be broken into sessions of up to 10 minutes duration in which testing is guided by these mission statements
B. Break the testing work in 30 to 120 minutes sessions and use properly defined mission statements consisting of two or three sentences to guide testing during these sessions
C. Define very generic charters to drive exploratory testing sessions of 2 days where testers are completely free to decide what to test
D. Exploratory testing should not be managed because such testing is inherently unmanageable and not measurable
Click for Answer
B. Break the testing work in 30 to 120 minutes sessions and use properly defined mission statements consisting of two or three sentences to guide testing during these sessions
Question # 7 Reviews You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects. You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project. On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects). Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario? Number of correct responses: 1 K4 3 credits
A. Management support
B. Participant support
C. Definition and use of metrics to measure the ROI (Return On Investment)
D. Training in the review process
Click for Answer
C. Definition and use of metrics to measure the ROI (Return On Investment)
Question # 8 People Skills – Team Composition An agile development team decides to hire a tester who has always worked: - in independent test teams, reporting the problems found in a defect tracking system - in safety-critical projects, with a stronger focus on the quality of the product than on time and budget. This agile team is focused on short-term goals to get the product released on time and within budget. Which of the following answers would you expect to be most likely true in this scenario? Number of correct responses: 1 K2 1 credit
A. Agile teams like the presence of a tester in their teams and the tester will be able to adapt to the new context without any issue
B. The developers will immediately follow the guidelines described by the tester
C. The tester can continue to report the problems found in a defect tracking system and be more focused on the quality than on time and budget constraints
D. The tester’s mission could be to verify adherence to requirements, instead of reporting formally the problems in a defect tracking system
Click for Answer
D. The tester’s mission could be to verify adherence to requirements, instead of reporting formally the problems in a defect tracking system
Up-to-Date
We always provide up-to-date CTAL-TM_Syll2012 exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the CTAL-TM_Syll2012 exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download ISTQB Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling CTAL-TM_Syll2012 practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied iSQI customer in this time. Our customers are our asset and precious to us more than their money.
CTAL-TM_Syll2012 Dumps
We have recently updated iSQI CTAL-TM_Syll2012 dumps study guide. You can use our ISTQB braindumps and pass your exam in just 24 hours. Our ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] real exam contains latest questions. We are providing iSQI CTAL-TM_Syll2012 dumps with updates for 3 months. You can purchase in advance and start studying. Whenever iSQI update ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] exam, we also update our file with new questions. Passin1day is here to provide real CTAL-TM_Syll2012 exam questions to people who find it difficult to pass exam
ISTQB can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with CTAL-TM_Syll2012 dumps. iSQI Certifications demonstrate your competence and make your discerning employers recognize that ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive iSQI exam dumps will enable you to pass your certification ISTQB exam in just a single try. Passin1day is offering CTAL-TM_Syll2012 braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download ISTQB dumps and access them at any device after purchase. Online ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] practice tests are planned and designed to prepare you completely for the real iSQI exam condition. Free CTAL-TM_Syll2012 dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my iSQI exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your CTAL-TM_Syll2012 exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.